# Constraint records between trades

An editorial proposal separating contractor completion reports, inspection verification, and subsequent handoff states by section.

## Core concepts

- Editorial proposal: Use separate columns for planned end date, contractor completion report, inspection verification, and subsequent handoff status for each section.
- Of 10 sections, 8 contractor completion reports and 6 inspection confirmations represent different states of 80% and 60%. Do not convert these into numbers of sections ready to start. Hand off unresolved evidence and verification owners for each section.

## Application conditions and usage

Comparing supplied schedules and site reports

## Limitations and scope

Not execution instructions for safe methods or work sequences. Uses a Korean employee introduction and U.S. and UK manager guides. Not all managerial work, including contracts and permits, falls within this site worker’s authority. The actual occupation includes site execution, whereas the AI draft supports review of supplied materials. Suitability of the name and support scope, and separation from adjacent roles, remain unreviewed.

## Judgment directions

- Compare planned end dates, contractor reports, inspection evidence, and handoff states separately by section.
- State denominators for status percentages and record unresolved evidence and owners. Do not turn completion-report percentages into counts ready for subsequent work.

## Sources

| Item | Content |
| --- | --- |
| Material | [Domestic building-construction job introduction, 2024-08-21](https://newsroom.hdec.kr/kr/newsroom/news_view.aspx?NewsListType=inter_list&NewsSeq=1083&NewsType=SOCIAL) |
| Author or organization | Hyundai Engineering & Construction Newsroom |
| Edition and date | Domestic building-construction job introduction; posted 2024-08-21; accessed 2026-10-20 |
| Region and context | South Korean employee example; delegated structural-design and work-permit scope unverified |
| Date checked | 2026-10-20 |

Independent summaries and editorial proposals composed by the author, with links to originals. No reproduction or redistribution of source text.

| Item | Content |
| --- | --- |
| Material | [Construction Managers 11-9021.00](https://www.onetonline.org/link/summary/11-9021.00) |
| Author or organization | O*NET OnLine |
| Edition and date | 11-9021.00; Updated 2026; accessed 2026-10-20 |
| Region and context | U.S. construction-manager duties, broader than the draft’s site-record support; contract and permitting authority is not transferred |
| Date checked | 2026-10-20 |

Independent summaries and editorial proposals composed by the author, with links to originals. No reproduction or redistribution of source text.

| Item | Content |
| --- | --- |
| Material | [Construction manager](https://nationalcareers.service.gov.uk/job-profiles/construction-manager) |
| Author or organization | National Careers Service |
| Edition and date | Construction manager; edition/revision date not verified; accessed 2026-10-20 |
| Region and context | UK manager career guide; not equivalent to Korean qualifications or site-worker authority |
| Date checked | 2026-10-20 |

Independent summaries and editorial proposals composed by the author, with links to originals. No reproduction or redistribution of source text.

## Linked personas

| Personas | Occupation |
| --- | --- |
| [Building site coordinator](https://personawiki.app/en/personas/building-site-coordinator) | Check prerequisites and unresolved issues across trades in supplied drawings, schedules and quality records, and prepare subcontractor queries, progress reports and handoff notes. |

## Editorial status

Editorial draft mapping to the public format. concepts preserves the existing body text unchanged. Summaries and application directions are the author’s proposals. Sources support actual occupational scope; this document supports comparison and handoff of supplied materials. It is not work authorization, equipment operation, professional diagnosis, or a safety or legal-conformity judgment. Awaiting practitioner and administrator review. Reuse labels describe the editorial method, not verified permission to reuse. Practitioner expert verification and proof of model effectiveness remain incomplete. Provided as editorial material at the site owner’s publication instruction. Editorial English translation of the Korean edition. No professional translation or occupational expert review has been completed. Translation does not change the source jurisdiction.

Sources were checked by the operator; occupational experts have not verified this editorial edition.

| API | Path |
| --- | --- |
| [JSON](https://personawiki.app/api/v1/knowledge/site-constraint-map?lang=en) | kb-30ac94bbbfee39ff |